FORM – III
Proforma for submission of information for the Quarter ending MARCH 2007
Name of the Trader : KARAM CHAND THAPAR & BROS. (C. S) LTD.
License details (No. & Date) : 13/Trading/CERC dated 27.01.2005
S No |
Volume of Trading in Million Units |
Purchased from |
Sold to* |
Point of purchase |
Purchase price (PAISE/KWH) |
Point of sale |
Sale Price (PAISE/KWH) |
Transmission/ wheeling charges borne by Seller/Trader/ Buyer** |
Transmission lossed borne by Seller/Trader/ Buyer** |
UI Charges borne by Seller/ Buyer** |
Trading margin charged |
Remarks |
1. |
0.33000 |
CESC |
PSEB (PUNJAB) |
CESC Periphery |
Off Peak 515 (Jan-07) |
PUNJAB Periphery |
Off Peak 519 (Jan-07) |
BUYER (PSEB) |
BUYER (PSEB) |
BUYER (PSEB) |
4 PAISE |
NIL |
2. |
3.54500 |
TNEB |
PSEB
(PUNJAB) |
TNEB Periphery |
(Jan-07) Midnight 577
(upto 50 MW) &
572 beyond 50 MW
Off Peak 581
(Feb -07) Midnight 603
(Mar-07) Midnight 644 |
PUNJAB Periphery |
(Jan-07) Midnight 581
(upto 50MW) &
576 beyond 50 MW
Off Peak 585
(Feb-07) Midnight 607
(Mar-07) Midnight 648 |
BUYER (PSEB) |
BUYER (PSEB) |
BUYER (PSEB) |
4 PAISE |
NIL |
3. |
9.40000 |
TNEB |
MPPTCL (MADHYA PRADESH) |
TNEB
Periphery |
……….DO……….. |
MP Periphery |
……….DO……….. |
BUYER (MPPTCL) |
BUYER (MPPTCL) |
BUYER (MPPTCL) |
4 PAISE |
NIL |
4. |
26.38250 |
TNEB |
RPPC (RAJASTHAN) |
TNEB
Periphery |
……….DO……….. |
RAJASTHAN Periphery |
……….DO……….. |
BUYER (RAJASTHAN) |
BUYER (RAJASTHAN) |
BUYER (RAJASTHAN) |
4 PAISE |
NIL |
Note : All the transactions shall be reported transaction-wise on real time basis and should not be aggregated.
*Besides the name of the seller/buyer, indicate the category of the seller/buyer namely generator, captive power plant, distribution licensee,Government, consumer (when applicable) etc.
**Strike out whichever is not applicable.
Dated : 4th APRIL, 2007.
|